Project Schedule

Please note this is a projected schedule which can be affected by weather and/or unforeseen conditions

Phase 1

November 6 to December 15, 2017 – Storm sewer and sidewalk will be installed

August 9 to August 22, 2018 –Milling, resurfacing, striping, signal loops

Phase 2

June 8, 2017 - Milling will begin in center of roadway for storm sewer

June 12, 2017 - Storm sewer installation will begin

June 19 to July 13, 2017 - North half of roadway will be removed, subgrade treatment will be performed

July 13 to August 3, 2017 - South half of roadway will be removed, subgrade treatment will be performed

August 10, 2017 - Paving will begin

August 16 to December 8, 2017- Driveways, sidewalk, and sod will be installed

August 9 to August 22, 2018 –Surface paved, striping, signs installed

Phase 3

October 9 to October 23, 2017 – Old SR 261 completely closed for 14 days for storm sewer installation and paving

October 23 to December 15, 2017 - Sidewalk will be installed

August 9 to August 22, 2018 –Surface paved, striping, signs, signal loops

Phase 4A

December 11, 2017 to April 6, 2018 - Storm sewer will be installed

April 9 to April 23, 2018 – North half of roadway will be removed, subgrade treatment will be performed

April 24 to May 7, 2018 – South half of roadway will be removed, subgrade treatment will be performed

May 8 to May 9, 2018 – Curb and gutter will be installed

May 10 to May 11, 2018 – Paving will begin

May 14 to June 15, 2018 - Driveways, approaches, and sidewalk will be poured

June 14 to June 20, 2018 – Sod preparation/installation

Phase 4B

March 23 to April 6, 2018- Storm sewer will be installed

May 8 to May 31, 2018 – North half of roadway will be removed, subgrade treatment will be performed

June 1 to June 22, 2018 - South half of roadway will be removed, subgrade treatment will be performed

June 26 to June 28, 2018 – Curb and gutter will be installed

June 29 to July 5, 2018 – Paving will begin

July 5 to August 8, 2018 - Driveways, approaches, and sidewalk will be poured

August 7 to August 15, 2018 – Sod preparation/installation

Final Work

August 9 to August 15, 2018 - Surface will be paved

August 16 to August 22, 2018- Signs, roadway striping

Expected substantial completion date is August 22, 2018.